Engineering

A division of the Town’s Public Services Department, the Engineering Division, is committed to serving the community by supporting Town departments with design and implementation of capital improvement projects including new sidewalks, paving projects, water and sewer lines, and Town facilities.

Below is a list of current Town projects:

West Wilson & West McLelland Improvement Projects October 2016


Transportation GO Bond Projects Map October 2016
 

FY18 Paving Projects
The list of streets that are part of the FY18 Paving Program are listed here.
 

Mill Village Sidewalk & Utilities (2014 GO Bond)

  • Construction in phases 2017 through 2020.
  • New sidewalk ( one side of the street) and curb & gutter to promote pedestrian walkability and also connectivity to the Downtown area.
  • Estimated Cost: $3,242,675
  • Replace Aging or undersized water and sewer lines.
  • Estimated Utility Fund Cost: $3,855,000
  • Mill Village Sidewalk Concept Plan
Mooresville School Network Sidewalk (2014 GO Bond)

  • New Sidewalk connecting Mooresville Middle School and Kistler Farm Road communities with Bellingham Park and Fieldstone/Magnolia Sidewalk Network.
  • Status: Project out for bid.
  • Estimated Cost: $3,700,000
  • Committed CMAQ Funding: $343,000
  • Requested Additional CMAQ Funding: $801,996
  • Total Bonded Cost: $534,754
  • Mooresville School Network Sidewalk Concept Plan
NC 115/Faith Road Intersection Improvements (2014 GO Bond)

  • Status: Utility relocates and authorization from NCDOT
  • Realignment of existing intersection for improved traffic flow along with new left turn lanes on all legs of the intersection.
  • Construction is expected to start Fall 2018 and last 18 months.
  • Estimated Cost: $1,205,895
  • Committed CMAQ Funding: $1,883,625
  • Developer's Portion: $253,000
  • Total Bonded Cost: $1,194,631
  • NC 115/Faith Road Concept Plan
NC 150/NC 115 Intersection Improvements (2014 GO Bond)

  • Status: Construction operations under way.
  • New right turn lanes on the west bound and south bound legs of the intersection.
  • Construction is expected to 14 months.
  • Construction Cost: $1,089,740
  • Committed CMAQ Funding: $1,398,782
  • Total Bonded Cost: $355,968
  • NC 150/NC 115 Concept Plan
NC 150/NC 801 Intersection Improvements (2014 GO Bond)

  • Status: Utility relocates and final plan review.
  • New left lanes on all legs of the intersection.
  • Construction is expected to begin Winter 2018 and last 18 months.
  • Estimated Project Cost: $2,249,800
  • Committed Bonus Allocation and CMAQ Funding: $1,919,976
  • Total Bonded Cost: $282,254
  • NC 150/NC 801 Concept Plan

West McLelland Avenue Improvements

  • Status: Finalizing and preparing for bidding.
  • Complete road reconstruction including sidewalk along West McLelland from Plaza Drive to Broad Street.
  • Construction to start Fall 2018.
  • Estimated Cost: $2,500,000

West Wilson Avenue Improvements

  • Status: Right-of-way phase.
  • New curb and pedestrian path including pedestrian bridge along West Wilson Avenue from NC 21 to Broad Street.
  • Construction to start Winter 2019.
  • Estimated Cost: $2,650,000
Liberty Park Renovation

  • Renovations will include a bandshell, event lawn, walking paths, landscaping, War Memorial walkway, public art and access from Church Street.
  • Plans are 95% complete and project is expected to be bid in October.
  • Construction could start by the end of the year and is expected to take approximately nine months
Selma Burke Center Renovation & Expansion

  • Project includes a new multi-purpose building, open space, playground, picnic shelter, walking paths, additional parking, new gym floor and upfits to the existing building.
  • Construction will begin in September and be completed no later than November 2019.
  • Total project cost is $4,760,600
  • $500,000 state grant received to assist with project cost.
Rocky River Outfall

  • Status: Under construction.
  • Gravity sewer from NC Highway 3 at Mooresville Intermediate School to Linwood Farms.
  • Expected completion date February 1, 2019.
  • Estimated Cost: $3,394,410
Mt. Mourne Outfall

  • Status: Under construction.
  • Gravity sewer from Presbyterian Road pump station to Intersection of Faith and Highway 115.
  • Expected completion date August 12, 2019.
  • Estimated Cost: $3,878,619

Langtree Force Main & Pump Stations

  • Status: Under construction.
  • Sewer force main and pump station to service southeast quadrant of Langtree Road & I-77.
  • Expected completion date June 2, 2019.
  • Estimated Cost: $2,270,480