The Town of Mooresville has projects either in the study, planning, and design phases, or actively under construction in each of the program areas listed below. Select the links to the program areas to learn more about the status of the projects.


 Selma Burke Center
 SELMA
The Selma Burke Center is undergoing renovation to the existing facilities and adding a new multipurpose space as well as new amenities to serve the recreational needs of Mooresville citizens. The projects design and construction administration has been awarded to Wirth and Associates along with Lutman Architecture. The construction contract for the renovations and new facilities has been awarded to Miles-McClellan Construction. Some of the major points of the project are:


 Liberty Park
Liberty Park is set for a multi-phased renovation beginning in 2019. The design of the park and its new amenities has been awarded to Stewart design. The project is in final phases of design and is set to be put out for bid in early 2019. The project includes:

  • New green space and walking paths.
  • New entrance to the park from Church Street.
  • Veteran's promenade and art installation.
  • New Bandshell and performance area.
  • Landscaping.
  • Liberty Park Rendering

 Mill Village Sidewalk & Utilities (2014 GO Bond)
 millvillage
  •  Construction in phases 2017 through 2020.
  • New sidewalk ( one side of the street) and curb & gutter to promote pedestrian walkability and also connectivity to the Downtown area.
  • Estimated Cost: $3,242,675
  • Replace Aging or undersized water and sewer lines.
  • Estimated Utility Fund Cost: $3,855,000
  • Mill Village Sidewalk Concept Plan

 Mooresville School Network Sidewalk (2014 GO Bond)
 schoolsidewalk
  • New Sidewalk connecting Mooresville Middle School and Kistler Farm Road communities with Bellingham Park and Fieldstone/Magnolia Sidewalk Network.
  • Status: Project out for bid.
  • Estimated Cost: $3,700,000
  • Committed CMAQ Funding: $343,000
  • Requested Additional CMAQ Funding: $801,996
  • Total Bonded Cost: $534,754
  • Mooresville School Network Sidewalk Concept Plan  

 NC 115/Faith Road Intersection Improvements (2014 GO Bond)
 faithroad
  • Status: Utility relocates and authorization from NCDOT
  • Realignment of existing intersection for improved traffic flow along with new left turn lanes on all legs of the intersection.
  • Construction is expected to start Fall 2018 and last 18 months.
  • Estimated Cost: $1,205,895
  • Committed CMAQ Funding: $1,883,625
  • Developer's Portion: $253,000
  • Total Bonded Cost: $1,194,631
  • NC 115/Faith Road Concept Plan

 NC 150/NC 115 Intersection Improvements (2014 GO Bond)
 150115
  • Status: Construction operations under way.
  • New right turn lanes on the west bound and south bound legs of the intersection.
  • Construction is expected to be 14 months.
  • Estimated Cost: $1,089,740.
  • Committed CMAQ Funding: $1,398,782.
  • Total Bonded Cost: $355,968
  • NC 150/NC 115 Concept Plan

 NC 150/NC 801 Intersection Improvements (2014 GO Bond)
 150115
  • Status: Utility relocates and final plan review.
  • New left lanes on all legs in the intersection.
  • Construction is expected to begin Winter 2018 and last 18 months.
  • Estimated Cost: $2,249,800.
  • Committed Bonus Allocation and CMAQ Funding: $1,919,976.
  • Total Bonded Cost: $282,254.
  • NC 150/NC 801 Concept Plan

West McLelland Avenue Improvements
  • Status: Finalizing and preparing for bidding.
  • Complete road reconstruction including sidewalk along West McLelland from Plaza Drive to Broad Street.
  • Construction to start Fall 2018.
  • Estimated Cost: $2,500,000.

West Wilson Avenue Improvements
  • Status:Right-of-way phase.
  • New curb and pedestrian path including pedestrian bridge along West Wilson Avenue from NC 21 to Broad Street.
  • Construction to start Winter 2019.
  • Estimated Cost: $2,650,000.

Rocky River Outfall
  • Status: Under construction.
  • Gravity sewer from NC 3 at Mooresville Intermediate School to Linwood Farms.
  • Expected completion date February 1, 2019.
  • Estimated Cost: $3.394.410.

Mt. Mourne Outfall
  • Status: Under construction.
  • Gravity sewer from Presbyterian Road pump station to Intersection of Faith Road and NC 115.
  • Expected completion date August 12, 2019.
  • Estimated Cost: $3,878,619.

Langtree Force Main & Pump Stations
  • Status: Under construction.
  • Sewer force main and pump station to service southeast quadrant of Langtree Road & I-77.
  • Expected completion date June 2, 2019.
  • Estimated Cost: $2,270,480.